Network maintenance - Reset port speeds on MCDC/WEMR Provider Edge routers

Scheduled Maintenance Report for TAMU Technology Services IT

Completed

The scheduled maintenance has been completed.
Posted Jul 13, 2025 - 13:51 CDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jul 13, 2025 - 12:00 CDT

Scheduled

Maintenance Date: Sunday, July 13, 2025


Maintenance Time: 12 pm (12:00) to 5 pm (17:00)


Details of Maintenance: Reconfigure the port speeds on MCDC-PE-1 and WEMR-PE-2 to accommodate more 100G connections. The line cards for each PE router requires a restart in order for the new ports speeds to take effect.

Impact to Customers: Due to hardware and path redundancy there should be no customer impact. However, the entire maintenance window is reserved in case there are any issues.


If you experience an outage past the above estimated end time, please contact TAMU-IT Help Desk Central at 979-845-8300. Any comments or questions concerning this maintenance should also be directed to TAMU-IT Help Desk Central.


TDX Change ID: 268166
Posted Jul 09, 2025 - 16:25 CDT
This scheduled maintenance affected: Infrastructure (Data Center Services).